Power and Desalination Plants Project - EIR 03-05

16 Documents in Project

Summary

SCH Number
2004041081
Lead Agency
City of Carlsbad
Document Title
Power and Desalination Plants Project - EIR 03-05
Document Type
NOD - Notice of Determination
Received
Posted
6/19/2006
Present Land Use
Public Utilities (U) for desalination plant site and surrounding power station. Land uses, zoning and General Plan designations vary for the offsite pipeline.
Document Description
The project is a proposal to (1) construct and operate a 50 million gallon per day seawater desalination plant and other appurtenant and ancillary water and support facilities to produce potable water, including an offsite water delivery pipeline system; and (2) establish a Precise Development Plan (PDP) for the Encina Power Station (EPS). The desalination plant would be located at the Encina Power Station in Carlsbad. The offsite pipeline system would extend into the cities of Carlsbad, Oceanside, and Vista. The PDP would serve as the primary City of Carlsbad land use application for the desalination plant and as a document to establish existing land uses at and development land use standards for the EPS. The project does not proposed to modify EPS operations or existing facilities, other than discharge channel and electrical connections.

Contact Information

Name
Scott Donnell
Agency Name
City of Carlsbad
Contact Types
Lead/Public Agency

Location

Cities
Carlsbad, Oceanside, San Marcos, Vista
Counties
San Diego
Cross Streets
Carlsbad Blvd. / Cannon Road
Zip
92008
Total Acres
4 + offsite pipe
Parcel #
Multiple
State Highways
I-5, SR-78
Railways
NCTD
Airports
Palomar-McClellan
Schools
Multiple
Waterways
Pacific Ocean, Aguas Hedionda Lagoon and tributary drainages
Township
Multi.
Range
Multi.
Section
Multi.

Notice of Determination

Approving Agency
City of Carlsbad
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.