Operation of Twin Oaks Valley Water Treatment Plant Modification Project

13 Documents in Project

Summary

SCH Number
2004041081
Lead Agency
Carlsbad, City of (City of Carlsbad)
Document Title
Operation of Twin Oaks Valley Water Treatment Plant Modification Project
Document Type
NOD - Notice of Determination
Received
Posted
2/16/2016
Present Land Use
Public Utilities (U) for desalination plant site and surrounding power station. Land uses, zoning and General Plan designations vary for the offsite pipeline.

Document Description
SWRCB will be issuing a water supply permit. The SD County Water Authority proposed project included the addition of a 10-mile conveyance pipeline, piping and valving changes, chlorine and ammonia monitoring and dosing equipment, upsizing existing pipeline, flowmeters, membrane backpulse tank, and modification to the solids handling facility at the Twin Oaks Valley Water Treatment Plant.

Contact Information
Sean Sterchi
SWRCB
1350 Front St
San Diego, CA 92101

Phone : (619) 525-4159

Location

Cities
Carlsbad San Marcos Vista
Counties
San Diego
Cross Streets
Carlsbad Blvd. / Cannon Road
Zip
92008
Total Acres
4 + offsite pipe
Parcel #
Multiple
State Highways
I-5, SR-78
Railways
NCTD
Airports
Palomar-McClellan
Schools
Multiple
Waterways
Pacific Ocean, Aguas Hedionda Lagoon and tributary drainages
Township
Multi.
Range
Multi.
Section
Multi.

Notice of Determination

Approving Agency
SWRCB
Approving Agency Role
Responsible Agency
Approved On
Final Environmental Document Available at
1350 Front St, Rm 2050, San Diego, CA 92101

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No
Download CSV New Search