Site Plan Review No. SPR-03-02 and Conditional Use Permit Application No. UP-03-23

2 Documents in Project

Summary

SCH Number
2004041048
Lead Agency
City of Seaside
Document Title
Site Plan Review No. SPR-03-02 and Conditional Use Permit Application No. UP-03-23
Document Type
NOD - Notice of Determination
Received
Posted
5/28/2004
Present Land Use
Parking Lot / Shopping Center / Retail Commercial
Document Description
The Applicant proposes to construct a 6,163 square foot restaurant with a full-service bar, outdoor patio and dedicated take-out area. The 15,126 square foot project leased pad/site is located west of the main entrance to the Laguna Grande Shopping Center and is currenlty being used for parking. Approximately 45 parking spaces will be eliminated by teh project. The restaurant will have 261 seats, which includes 227 seats inside and 34 seats in the outdoor patio area. The patio will be uncovered. The standard hours of operation of the restaurant are 4 PM to 1:00 AM daily. On seven to eight special holidays, the hours of operation will be from 10:00 AM to to 1:00 AM.

Contact Information

Name
Rick Medina
Agency Name
City of Seaside
Contact Types
Lead/Public Agency

Location

Cities
Seaside
Counties
Monterey
Cross Streets
SR 1 Northbound Ramp and Del Monte Blvd.
Zip
93955
Total Acres
5.6
Parcel #
011-561-013, -014, -015, -016, -017
State Highways
SR-1
Railways
Monterey Branch Line
Schools
Del Monte School site and Chartwell School
Waterways
Monterey Bay

Notice of Determination

Approving Agency
City Council of the City of Seaside
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.

Download CSV New Search Print