Windsor River Road Project

2 Documents in Project

Summary

SCH Number
2004032033
Lead Agency
Town of Windsor
Document Title
Windsor River Road Project
Document Type
NOD - Notice of Determination
Received
Posted
4/27/2004
Present Land Use
Project is within Town street right-of-way; adjacent zoning is Zone RS - Surrounding Residential.
Document Description
Construction of the project is anticipated to begin in June 2004 and continue for approximately three to four months. Construction phases would include clearing and grading; utility pole relocations; storm drain installation; installation of the bicycle lanes, curbs, gutters and sidewalks and parking; paving; post construction cleanup; and site restoration. Improvements to widen Windsor River Road to 39 feet (curb-to-curb, typical) will be accomplished by narrowng the two lanes from 12 to 11 fet, and installing "traffic calming" measures (such as bulbouts), which serve to slow traffic. The bicycle lanes will be five (5) feet wide, and the sidewalks will generally be 5.5 feet wide. Ina ddition, ornamental street lighting will be installed as part of the project.

Contact Information

Name
Stuart Hayre
Agency Name
Town of Windsor
Contact Types
Lead/Public Agency

Location

Cities
Windsor
Counties
Sonoma
Cross Streets
Starr Road to Windsor Road
Zip
95492
Total Acres
length = 2,600 f
State Highways
101
Railways
NWPRA/SMART
Schools
Windsor High & Cali Calmemac

Notice of Determination

Approving Agency
Town of Windsor
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
No

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.