Kings River Conservation District Peaking Plant

2 Documents in Project

Summary

SCH Number
2004031053
Lead Agency
California Energy Commission
Document Title
Kings River Conservation District Peaking Plant
Document Type
NOD - Notice of Determination
Received
Posted
5/19/2004
Present Land Use
Industrial
Document Description
The KRCDPP is a simple cycle plant consisting of two General Electric LM 6000 Sprint PC model, natural gas combustion turbines generating approximately 97 MW of electricity. The proposed project includes the construction of a single 115 KV transmission line, water supply line and zero liquid discharge system.

Contact Information

Name
Jack W. Caswell
Agency Name
California Energy Commission
Contact Types
Lead/Public Agency

Location

Counties
Fresno
Cross Streets
North Avenue
Total Acres
9.5
Other Location Info
Malaga

Notice of Determination

Approving Agency
California Energy Commission
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
N/A

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print