Water Pollution Control Plant (WPCP) Outfall Project (Project); Clean Water State Revolving Fund (CWSRF) No. C-06-4997-120
8 Documents in Project
Summary
SCH Number
2004022111
Lead Agency
City of Chico
Document Title
Water Pollution Control Plant (WPCP) Outfall Project (Project); Clean Water State Revolving Fund (CWSRF) No. C-06-4997-120
Document Type
NOD - Notice of Determination
Received
Posted
6/16/2009
Present Land Use
Public/Quasi Public Facilities (Water Pollution Control Plant) / Agricultural land (outfall)
Document Description
The project involves constructing a new outfall pipeline and diffuser to replace the existing pipeline and diffuser. The existing outfall diffuser is designed to handle 12 million gallons per day (MGD) of wet weather flow. The new outfall pipeline and diffuser will be designed to handle 37.5 MGD of peak wet weather flow (PWWF) to match the designed PWWF of the existing WPCP at future build-out. The existing outfall will be abandoned, capped, and sealed once the new outfall is constructed.
Contact Information
Name
Lisa Lee
Agency Name
State Water Resources Control Board
Contact Types
Lead/Public Agency
Phone
Location
Cities
Chico
Counties
Butte
Cross Streets
4827 Chico River Road
Zip
95928
Total Acres
123
Parcel #
039-530-009,010,018
Waterways
Sacramento River, Big Chico Creek
Notice of Determination
Approving Agency
State Water Resoures Control Board
Approving Agency Role
Responsible Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes