New Almaden Trail Reroute and Pedestrian Bridge Replacement

2 Documents in Project

Summary

SCH Number
2004022014
Lead Agency
Santa Clara County
Document Title
New Almaden Trail Reroute and Pedestrian Bridge Replacement
Document Type
NOD - Notice of Determination
Received
Posted
4/19/2004
Present Land Use
Existing Park / HS / Hillsides
Document Description
The project consists of trail realignments at two sites along the New Almaden Trail, and a replacement and relocation of a degraded unsafe pedestrian bridge. Both sites are in Almaden Quicksilver County Park. Site A is a re-routing of an existing trail above and around a section of an area subject to land slides and where erosion has washed out a section of the existing rail. A temporary walkway has been constructed over the washed out section of trail. Site B is re-routing of an existing trail to reduce the grade of the current trail, which exceeds 20% at some points, and to replace an existing degraded pedestrian bridge. The current bridge location is approached by a steep section of trail (approximately 30% grade) which is eroded; the bridge tread and supports are degraded and unstable (see photo 1). This bridge will be replaced and moved downstream to a site with greater bank stability, and approached by the new, less steeply graded trail alignment.

Contact Information

Name
Antoinette Ramos
Agency Name
Santa Clara County Parks and Recreation Department
Contact Types
Lead/Public Agency

Location

Cities
San Jose
Counties
Santa Clara
Cross Streets
McAbee Road
Parcel #
575-10-008

Notice of Determination

Approving Agency
Santa Clara County Board of Supervisors
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
N/A
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
N/A

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print