Industrial Technology Center Phase 1 (Manufacturing Technology Center)

3 Documents in Project

Summary

SCH Number
2003111134
Lead Agency
Long Beach Community College District
Document Title
Industrial Technology Center Phase 1 (Manufacturing Technology Center)
Document Type
NOD - Notice of Determination
Received
Posted
2/11/2004
Present Land Use
College campus is used as educational facility and parking/Land Use District Nuber 10 - Institutions/Schools/Institutional (1) Zoning
Document Description
The proposed project is the Industrial Technology Center - Phase I (Manufacturing Technologies Center), Long Beach City Collge, Pacific Coast Campus. The project includes: the demolition of Building #22 (UU) Machine Shop - 8,383 assignable square feet (ASF) and Building #27 (VV) Welding - 5,922 ASF; the removal of the masonry portion of Building #23 (MM) - 1,384 ASF; and the construction of new Industrial Technology Center - Phase I - 22,119 ASF. The existing buildings were built in 1958 (UU), 1953 (VV), and 1953 (MM) and have health and safety hazards. While these facilities are currently used for instruction, the buildings are out of date, have numerous safety problems related to Cal OSHA requirements, and are unsuitable for modern day manufacturing technologies. The new Industrial Technology Center - Phase I will include: welding, heating and air-conditioning, sheet metal facilities, and plumbing programs. The net increase in ASF is 5,481. The replacement building will be a two-story facility.

Contact Information

Name
Eloy Oakley
Agency Name
Long Beach Community College District
Contact Types
Lead/Public Agency

Location

Cities
Long Beach
Counties
Los Angeles
Cross Streets
Pacific Coast Highway and Walnut
Zip
90806
Total Acres
+/- 0.93
Parcel #
Unknown
State Highways
I405 and PCH1
Airports
Long Beach Municipal
Schools
Mary Butler

Notice of Determination

Approving Agency
Board of Trustees of the Long Beach Community College District
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.