North Haiwee Dam No. 2 Geotechnical Investigations and Archaeological Resources Testing for the Haiwee Power Plant Penstock Replacement Project; California Enda

7 Documents in Project

Summary

SCH Number
2003091085
Lead Agency
Los Angeles County
Document Title
North Haiwee Dam No. 2 Geotechnical Investigations and Archaeological Resources Testing for the Haiwee Power Plant Penstock Replacement Project; California Enda
Document Type
NOD - Notice of Determination
Received
Posted
3/9/2015
Present Land Use
Natural Resources
Document Description
This proposed project amendment involves additional geotechnical trenches and dozer cuts (scraping of the existing surface) to be constructed in order to locate an active earthquake fault. The trenches would measure approximately 300 feet long, 5 to 20 feet deep and approximately 30 to 100 feet wide. The project amendment also includes Archaeological Resources Testing for the Haiwee Power Plant Penstock Replacement Project intended to evaluate each of 19 archaeological sites for their significance under Section 106 of the National Historic Preservation Act (NHPA) and/or the California Environmental Quality Act (CEQA). The Project includes disturbance of up to 25 acres of undeveloped land as a result of trench digging, borings, mechanized excavation, shovel scrapes, shovel test units, controlled excavation units and Project area access. The Project will result in temporary impacts up to 10 acres of Mohave ground squirrel (Spermophilus mohavensis) and desert tortoise (Gopherus agassizii) habitat. The project is expected to result in incidental take of Mohave ground squirrel and desert tortoise which are designated as threatened species under the California Endangered Species Act. The ITP referenced above as issued by CDFW authorizes incidental take of species listed under CESA that may occur as a result of Project implementation.

Contact Information

Name
Leslie MacNair
Agency Name
CDFW Inland Deserts Region
Contact Types
Lead/Public Agency

Location

Counties
Inyo
Cross Streets
Owens Valley & Sierra Nevada
Total Acres
4.5
State Highways
395
Township
19/20S
Range
37E
Section
33/34
Base
MDBM
Other Location Info
southern End Owens Valley, north end Haiwee Reservoir
Other Information
Section: 3 & 4

Notice of Determination

Approving Agency
CDFW
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.