Protective Betterment Project Near Schooner Gulch

4 Documents in Project

Summary

SCH Number
2003072128
Lead Agency
California Department of Transportation, District 1
Document Title
Protective Betterment Project Near Schooner Gulch
Document Type
NOD - Notice of Determination
Received
Posted
12/26/2003
Present Land Use
Caltrans-Transportation USE; Adjacent land zoned RL60 amd RMR40
Document Description
This project proposes to realign Route 1 in Mendocino County about four miles south of Point Arena from post mile 10.7 to post mile 11.3 where the roadway is deteriorating due to substantial coastal erosion. The realigned section will consist of two twelve-foot lanes and two four-foot paved shoulders. Other project features include: vista turnouts, removal of the portion of bypassed roadway and temporary bridge, improved driveway access, culvert installation, revegetation of disturbed soils and implementation of a wetland mitigation plan within the realignment, the existing highway and at the Hearn Gulch Scenic Vista Overlook approximately one mile south of the project. The project is required to assure that the roadway will remain operational for a minimum design life of twenty years.

Contact Information

Name
Devorah L. Harmon
Agency Name
Department of Transportation, District 1
Contact Types
Lead/Public Agency

Location

Cities
Point Arena
Counties
Mendocino
Cross Streets
Route 1, Post Mike 10.7-11-3
Total Acres
.5 miles of Hwy.
State Highways
1
Waterways
Pacific Ocean, Schooner Gulch, Hearn Gulch
Township
12N
Range
44E
Section
32
Base
Sauders

Notice of Determination

Approving Agency
California Department of Transportation
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.