The corridor travels through primarily urban, built-out commercial and industrial areas, county parklands, and open space areas.
Document Description
The proposed project would convert an existing 60 kV line to a 115 kV line on an approximately 12-mile stretch between the San Mateo and Martin Substations. The project includes replacing the existing #4 circuit wires and insulators on the San Mateo-Martin #4 60 kV power line with new wires as well as modifications at the existing San Mateo, Burlingame, Millbrae, and Martin Substations.

Contact Information

Name
CA Public Utilities Commission
Agency Name
Public Utilities Commission
Contact Types
Lead/Public Agency

Location

Cities
Brisbane, Burlingame, Daly City, Daly City, South San Francisco, San Bruno, Millbrae, ..., Millbrae, San Bruno, San Mateo, South San Francisco
Counties
San Mateo
State Highways
US 101
Railways
Union Pacific / BART
Airports
SFO
Schools
~9 Schools
Waterways
Burlingame Lagoon, Navigable Slough

Notice of Determination

Approving Agency
California Public Utilities Commission
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.