Chaffey Community College Campus Master Plan
5 Documents in Project
Summary
SCH Number
2003071013
Lead Agency
Chaffey Community College
Document Title
Chaffey Community College Campus Master Plan
Document Type
NOD - Notice of Determination
Received
Posted
5/21/2004
Present Land Use
General Plan: Public Facilities
Zoning: Public Facilities
Land Use: Public Facilities
Document Description
The proposed Facilities Master Plan includes a series of projects for the campus that involve development of several new buildings, renovation of existing buildings, modifications to access and circulation, provision of additional parking and modification and expansion of other campus infrastructure. The development proposed under the Facilities Master Plan is intended to accommodate approximately 20,000 students at the Rancho Cucamonga campus by 2010. The campus currently has 306,220 Assignable Square Feet (ASF) of bulding space. To accommodate the projected 2010 student population of approximately 20,000 the campus needs to increase its building space to 494,405 ASF. As proposed, the Facilities Master plan would provide for the addition of 188,185 addional ASF of buiding space for a total ASF of 501,607. The sizes and uses in the Facilities Master Plan are programmatic in nature and not specific. A detailed program of space types and sizes will be identified as each facility is developed.
Contact Information
Name
David Wollenberg
Agency Name
Chaffey Community College
Contact Types
Lead/Public Agency
Phone
Location
Cities
Rancho Cucamonga
Counties
San Bernardino
Cross Streets
Wilson Avenue/Banyan Street/ Haven Avenue
Zip
91737
Total Acres
200
State Highways
210
Township
7S
Range
7W
Section
25
Base
25
Notice of Determination
Approving Agency
Chaffey Community College District
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
N/A
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.