Document Description
The proposed project would construct a storm drain system for the proposed shopping center and connect the new system into the existing outlet. The new storm drain system would be constructed using 48-inch diameter high-density polyethylene pipe (HDPE) tied into the existing outlet, which would be replaced using a 60-inch HDPE culvert with a flared end section. A concrete bulkhead would be constructed to support and anchor the outlet in place. Rock slope protection, approximately 12-inches in diameter, would be placed at the outlet to dissipate the energy of water exiting the flared end section. Oil and grease separators would be installed in the system and maintained at appropriate intervals to reduce or eliminate the introduction of petroleum-based pollutants into the Salinas River. A minor amount of riparian willow habitat would be trimmed to allow access to the site. The California Department of Fish and Game is executing a Lake and Streambed Alteration Agreement Number 1600-2003-0122-3 pursuant to Section 1603 of the Fish and Game Code to the project operator.

Contact Information

Name
Bill Farrel
Agency Name
Department of Fish and Game, Region 3
Contact Types
Lead/Public Agency

Location

Cities
Soledad
Counties
Monterey

Notice of Determination

Approving Agency
California Department of Fish and Game
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
N/A
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
N/A

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.