Carson Terminal Expansion

4 Documents in Project

Summary

SCH Number
2003061130
Lead Agency
City of Carson
Document Title
Carson Terminal Expansion
Document Type
NOD - Notice of Determination
Received
Posted
2/27/2004
Present Land Use
Heavy Industrial MH (Manufacturing, Heavy)
Document Description
Kinder Morgan Tank Storage Terminals LLC, a subsidiary of Kinder Morgan Energy Partners, L.P. (KMEP) is proposing to increase the storage capacity of their Carson Terminal, located adjacent to the southeast intersection of Alameda Street and Sepulveda Boulevard in the City of Carson, California. The project includes the installation of new tankage and supporting piping, pumps and ancillary equipment. The new tanks would meet the current demand for product storage and add capacity for future growth. Specifically, a total of 18 new 80,000-barrel product storage and one new 30,000 transmix storage tank with related piping, pumps and control systems would be constructed. Construction of the project would require filling a remnant of the old Dominguez Channel, which runs through the southwestern portion of the site.

Contact Information

Name
John Signo
Agency Name
City of Carson
Contact Types
Lead/Public Agency

Location

Cities
Carson
Counties
Los Angeles
Cross Streets
Alameda Street/Sepulveda Boulevard
State Highways
I-110,405,710;SR-1,103
Railways
Union Pacific
Waterways
Dominguez Channel
Township
4S
Range
13W
Section
Unname
Base
LB

Notice of Determination

Approving Agency
City of Carson
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes