Completion of Phase 2 Development at Lamb Canyon Landfill Project

5 Documents in Project

Summary

SCH Number
2003061074
Lead Agency
Riverside County
Document Title
Completion of Phase 2 Development at Lamb Canyon Landfill Project
Document Type
NOD - Notice of Determination
Received

Document Description
California Department of Fish and Game is executing a Alek and Streambed Agreement (SAA# 1600-2004-0100-R6) pursuant to Section 1602 of the Fish and Game Code to the project applicant, the Mr. Hans W. Kernkamp, General Manager-Chief Engineer of the Riverside County Waste Management Department. For Phase II, Stage 2, of the Lamb Canyon Class III Sanitary landfill expansion, the Operator proposes to expand the disposal area by 66.3 acres and the total landfill area by 175.3 acres. The project will permanently impact 1.174 acres of sparsely vegetated (mulefat) ephemeral streambeds. Of the previously authorized impacts, 1.120 acres have been completed including 0.825 acres within Drainages C and D and 0.296 acres within Drainages B, E, F, and H. The remaining proposed impacts under the new Agreement include the remaining 0.054 acres from the 2004 Agreement as well as the fill of 0.16 acres of newly reestablished jurisdictional waters within Drainage F, for a total of 0.214 acres of permanent impacts.

Contact Information
Ryan Ross
California Department of Fish and Game
Eastern Sierra-Inland Deserts Region 6
Los Alamitos, CA 90720

562 430 7212

Location

Cities
San Jacinto Beaumont
Counties
Riverside
Cross Streets
Gilman Springs Road
Zip
92223
Total Acres
1,088
Parcel #
421-170-034; 421-200-023, 024, 033; 421-220-014, 023, 024, 025, 026; 421-230-008, 009
State Highways
79
Township
3S
Range
1W
Section
21,28,
Base
SBBM
Other Information
Section (cont): 29

Notice of Determination

Approving Agency
CDFG
Approving Agency Role
Responsible Agency
Approved On
Final EIR Available Location
N/A

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A Statement of Overriding Considerations was adopted for this project
No
(5) Findings were made pursuant to the provisions of CEQA
Yes
Download CSV New Search