Lucchesi, Tony

3 Documents in Project

Summary

SCH Number
2003052102
Lead Agency
Humboldt County
Document Title
Lucchesi, Tony
Document Type
NOD - Notice of Determination
Received
Posted
8/26/2003
Present Land Use
Residential, Agricultural, Timber Residential, Agricultural, Timber Residential, Agricultural, Timber 5
Document Description
A Parcel Map Subdivision of a 30.8 acre parcel into two parcels of 5 acres and 25 acres and 25.8 acres. The smaller 5 acre parcel on the east side of Jacoby Creek (Parcel 1) is already developed with a single family residence. The larger parcel to the west of Jacoby Creek (Parcel 2) is undeveloped. It has been historically used for timber production. Both properties will take access off an old logging road that intersects with Jacoby Creek Road. An exception to the standard 50' lot frontage requirement on a publicly maintained road has been requested for Parcel 2; there is no frontage proposed for this lot. Instead, access to the parcel will be over a 20' easement that follows the old logging road. Improvement of this access will involve road improvements, including the installation of a 60 foot bridge across Jacoby Creek. A Special Permit is also required for bridge placement within the Streamside Management Area (SMA). Both parcels will be served by public water and individual sewage disposal systems.

Contact Information

Name
Michael Richardson
Agency Name
Humboldt County Planning Department
Contact Types
Lead/Public Agency

Location

Counties
Humboldt
Cross Streets
Jacoby Creek and Sonnefelt Road
Zip
95525
Total Acres
30
Parcel #
502-031-60
State Highways
101
Schools
Jacoby Creek
Waterways
Jacoby Creek
Township
5N
Range
1E
Section
11
Base
HM
Other Location Info
Jacoby Creek

Notice of Determination

Approving Agency
Humboldt County Planning Commission
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.