Stevens Creek Crib Wall
Summary
SCH Number
2003049021
Lead Agency
Fish & Game #3
Document Title
Stevens Creek Crib Wall
Document Type
NOD - Notice of Determination
Received
Posted
4/10/2003
Document Description
The proposed project involves stabilizing the northern bank of Stevens Creek by the construction of a reinforced concrete crib wall as described in the Swanson Hydrology and Geomorphology (2/28/2003) project plans. This concrete crib wall is a Caltrans standard "Type C" crib wall and is fourteen feet tall and thirty six feet long. The footing of the crib wall will be located approximately four feet below the base of the channel. The toe of the crib wall will be faced with a system of anchored root wads, stabilized by multi-sized rock-slope protection, and revegetated with native willow trees, as well as other native vegetation. The vegetated rock slope protection will require approximately 40 cubic yards of half-ton rock, one "aqua log," and two redwood logs. A mechanically stabilized earth (MSE) slope with a 1.5:1 slope will extend from the top of the crib wall to the top of the existing bank. The new MSE slope will match adjacent stream bank slopes, provide necessary stabilization to the fill area, and will be revegetated with native plants ecologically suitable to the local riparian corridor.
Contact Information
Name
Jim Mackenzie
Agency Name
Department of Fish and Game, Region 3
Contact Types
Lead/Public Agency
Address
Phone
Location
Cities
Los Altos
Counties
Santa Clara
Notice of Determination
Approving Agency
California Department of Fish and Game
Approving Agency Role
Responsible Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
N/A
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
N/A
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.