Guenoc Water Rights Modification Project
9 Documents in Project
Summary
SCH Number
2003042171
Lead Agency
State Water Resources Control Board
Document Title
Guenoc Water Rights Modification Project
Document Type
NOD - Notice of Determination
Received
Posted
6/25/2009
Document Description
The MND was prepared for closure of a waste management facility that formerly accepted liquid and solid wastes produced by geothermal exploration, steam power generation and other geothermal related activities. Closure will generally consist of consolidation and capping of the waste. The Division of water Rights is evaluation one of the mitigation projectsm which is lowering the elevation of Freeman Lake to ensure separation between groundwater and the landfill waste. Water will be used at Freeman Lake for fish and wildlife enhancement at the lake and the adjacent area, in addition to irrigation and stockwatering.
Contact Information
Name
Katherine Mrowka
Agency Name
State Water Resources Control Board
Contact Types
Lead/Public Agency
Phone
Location
Counties
Lake, Napa
Cross Streets
Butts Canyon Road
Zip
95461
Total Acres
6,847
Parcel #
multiple lake/napa
Waterways
Putah Creek, Bucksnort Creek, Butcherknife Creek, Routan Creek, Cassidy Creek
Township
10,11N
Range
5,6W
Base
MDB&M
Other Location Info
City/Nearest Community: Middletown
Other Information
Sec: multiple
Notice of Determination
Approving Agency
State Water Resources Control Board, Division of Water Rights
Approving Agency Role
Responsible Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.