Emergency Response Center Project
5 Documents in Project
Summary
SCH Number
2003042128
Lead Agency
University of California Santa Cruz
Document Title
Emergency Response Center Project
Document Type
NOD - Notice of Determination
Received
Posted
6/3/2004
Present Land Use
Public Facilities
Document Description
The project will construct an Emergency Response Center (ERC) and an associated Equipment Storage Building (ESB) on the UCSC campus. The ERC will be located on a 2.25-acre site on the south edge of the UCSC campus in the campus Corporation Yard and will provide space for the campus Emergency Operations Center, the Public Safety Dispatch Center, and the Campus Police Department. ERC will include the following primary elements: (a) construction of a 13,800 outside gross square feet (ogsf), two-story "L-shaped" building for the ERC; (b) development of parking areas and a short fire access road; (c) development of a courtyard for emergency events and general use; (d) installation of a stormwater management system; (e) installation of a communication tower; (f) installation of utility extensions and connections to existing services; and (g) installation of landscaping.
Contact Information
Name
John Zimmermann
Agency Name
University of California
Contact Types
Lead/Public Agency
Phone
Location
Cities
Santa Cruz
Counties
Santa Cruz
Cross Streets
Bay Street/High Street
Zip
95064
Total Acres
2.8 (2.55&.55)
Parcel #
01-011-11
State Highways
1, 9, 17
Schools
UC Santa Cruz
Township
11S
Range
2W
Section
10
Base
SC
Notice of Determination
Approving Agency
University of California
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.