Water Tank and Pipeline Replacement Project
2 Documents in Project
Summary
SCH Number
2003042078
Lead Agency
City of Rio Dell
Document Title
Water Tank and Pipeline Replacement Project
Document Type
NOD - Notice of Determination
Received
Posted
7/17/2003
Document Description
City of Rio Dell to install new transmission mains and new water storage tanks as replacements for existing facilitites to decrease water losses in the system. The project will increase the available water and allow for the redirection of operations and maintenance efforts to address deferred maintenance.
Contact Information
Name
Steve McHaney
Agency Name
City of Rio Dell
Contact Types
Lead/Public Agency
Phone
Location
Cities
Rio Dell
Counties
Humboldt
Cross Streets
Davis Street
Zip
95562
State Highways
101
Waterways
Eel River
Township
1N
Range
1E
Section
5
Base
HBM
Notice of Determination
Approving Agency
City of Rio Dell
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.