Addendum #4 to the Final EIR for the Sedgwick Reserve Infrastructure Plan - Sedgwick Reserve Offices and Accommodations Project-Garage #1 and #2 Reconstruction

8 Documents in Project

Summary

SCH Number
2003041096
Lead Agency
University of California, Santa Barbara
Document Title
Addendum #4 to the Final EIR for the Sedgwick Reserve Infrastructure Plan - Sedgwick Reserve Offices and Accommodations Project-Garage #1 and #2 Reconstruction
Document Type
NOD - Notice of Determination
Received
Posted
7/9/2018
Present Land Use
Academic/Research
Document Description
The Santa Barbara Campus proposes to demolish two structures, Garage #1 (660 sq. ft.) and Garage #2 (748 sq ft.) at the Sedgwick Reserve and rebuild them as office space and accommodations, respectively, for researchers at the Reserve. The Sedgwick Reserve Infrastructure Plan Final EIR included an evaluation of demolishing Garage #1 and retaining Garage #2. The proposed project would demolish both structures and rebuild them in the same size and building footprint. Garage #1 would become the LaKrez Director's and researcher's office and Garage #1 would become researcher accommodations. A new septic system would be installed to serve the researcher's accommodations.

Contact Information

Name
Shari Hammond
Agency Name
University of CA, Santa Barbara
Contact Types
Lead/Public Agency

Location

Counties
Santa Barbara
Cross Streets
Brinkerhoff and Roblar Avenues
Total Acres
6
Parcel #
133-16-056
State Highways
217
Airports
Santa Barbara
Waterways
Goleta Slough
Other Location Info
Nearest City: Los Olivos

Notice of Determination

Approving Agency
University of CA, Santa Barbara
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.