Downtown Bus Stopover and Multi-Use Facility

21 Documents in Project

Summary

SCH Number
2003041001
Lead Agency
City of San Diego
Document Title
Downtown Bus Stopover and Multi-Use Facility
Document Type
NOD - Notice of Determination
Received
Posted
6/27/2016
Present Land Use
The project site is located within the Ballpark Village Master Plan area, whoch is located east/southeast of the Petco Park ballpark within the Est Village neighborhood of the Centre City Community Plan area.
Document Description
The project consists of the construction and operation of a bus stopover and multi-use faiclity on one city block bounded by A Street, Union Street, B Street, and State Street (located within the Columbia Neighborhood within Downtown San Diego). The bus stopover facility would be used by buses and MTS operators, supervisors, and maintenance staff; no passenger boardings or alightings would take place there. A total of up to 24 bus bays would be needed to provide the required vehicle capacity to serve existing and near future local and BRT services. The multi-use facility would consist of up to approx. 300,000 sq. ft. of office use, 20,000 sq. ft. of retail use, and 280,000 sq. ft. of residential uses. Pursuant to CEQA Guidelines Section 15183.3, an Infill Environmental Checklist was prepared for this project documenting why no further CEQA review is required.

Contact Information

Name
Cheryle Hodge
Agency Name
San Diego Assoc. of Governments
Contact Types
Lead/Public Agency

Location

Cities
San Diego
Counties
San Diego
Cross Streets
Park Boulevard, Imperial Avenue, 11th Avenue, and Harbor Drive
Railways
yes

Notice of Determination

Approving Agency
San Diego Association of Governments
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
N/A
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print