Canyon del Rey Creek Sediment Retention Pond

Summary

SCH Number
2003039007
Lead Agency
Monterey County
Document Title
Canyon del Rey Creek Sediment Retention Pond
Document Type
NOD - Notice of Determination
Received
Posted
3/5/2003
Document Description
Canyon del Rey Creek is an ephemeral stream located at the north end of Silver Cloud Court near the intersection of Highway 68 and York Road in Monterey County. The stream channel contains water that strikes the hillside during and following rainstorms. The channel in this area ranges from two (2) to four (4) feet in width and one (1) to two (2) feet in depth and flows directly into a storm drain at the southern end of the property. Upstream from the project would construct a low earthen bem uphill from the site of an office park to create a sediment retention pond. The berm would be approximately six (6) to eight (8) feet high. A 36-inch round pipe would be placed in the pond just upstream from the berm. The pipe would be capped with a strainer and would contain 6-inch diameter openings to allow water to flow into an underground culvert made of 12-high density polyethylene pipe, where it would then flow into the existing storm drain system. The California Department of Fish and Game is executing a Lake and Streambed Alteration Agreement Number R3-2002-0751 pursuant to Section 1603 of the Fish and Game Code to the project operator, Mr. Leonard McIntosh.

Contact Information

Name
Dale Ellis
Agency Name
Monterey County Planning & Building Inspection
Contact Types
Lead/Public Agency

Location

Counties
Monterey

Notice of Determination

Approving Agency
CDFG
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
N/A
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
N/A

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.