Merced City School District Ranchero Lane School Site
2 Documents in Project
Summary
SCH Number
2003031038
Lead Agency
Merced City School District
Document Title
Merced City School District Ranchero Lane School Site
Document Type
NOD - Notice of Determination
Received
Posted
6/5/2003
Present Land Use
Vacant Land, A-R Agricultural Residential, RRC Rural Residential Center
Document Description
CSD proposes to acquire six adjacent land parcels to construct a new joint elementary and middle school facility with community center and a possible public park/sports field area at the Ranchero Lane site. MCSD proposes that acquisition of the lands and construction of a new multi-use facility will enable MCSD to accommodate the educational and community center needs of the increasing local population. Components of the proposed new joint school will include ADA-accessible classrooms to accommodate approximately 600 elementary school students, 1,000 middle school students and 110 faculty and other positions; multi-purpose room for student use and as a community center; recreation fields and courts; student drop-off, pick-up and parking areas; fencing; and other ancillary needs.
Contact Information
Name
Michael Carter
Agency Name
Merced City School District
Contact Types
Lead/Public Agency
Phone
Location
Cities
Merced
Counties
Merced
Cross Streets
Ranchero Lane and Dan Ward Road
Zip
95340
Total Acres
37.55
Parcel #
057-380-32 and 057-590-01,02,03,04, and 05
State Highways
99
Railways
Atchison Topeka,Santa Fe,SPRR
Schools
Franklin School
Waterways
Hesse Lateral,Bear Creek, & Black Rascal Slough,Lateral Canals and Drains
Township
7S
Range
13E
Section
15
Base
MDB&M
Notice of Determination
Approving Agency
Merced City School District
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes