Castaic Lake Water Agency (Santa Clarita Water Division) Sky Blue Tank Site Additions

3 Documents in Project

Summary

SCH Number
2003031004
Lead Agency
Castaic Lake Water Agency
Document Title
Castaic Lake Water Agency (Santa Clarita Water Division) Sky Blue Tank Site Additions
Document Type
NOD - Notice of Determination
Received
Posted
5/1/2003
Present Land Use
Varied
Document Description
The proposed project's objective is as follows: - To provide water during peak hour water usage periods to the Shapell/Monteverde project, a 2,500-unit residential development that is under construction north of the site. The proposed project would complete the water supply for this residential development. The proposed project is the construction of two above ground water storage tanks and an associated storm drainage system on a site that is owned by the Castaic Lake Water Agency. This site already contains a 1-million-gallon water tank and a 2-million-gallon water tank operated by the Castaic Lake Water Agency, Santa Clarita Water Division ("CLWA/SCWD"). Access to the site would be provided by the existing access road off of Whites Canyon Road just north of Enderly Street. The site is entered through a locked gate and is not accessible to the public. The proposed tanks would provide water during peak hour water usage periods to the Shapell/Monteverde project, a 2,500 unit residential development that is under construction north of the site.

Contact Information

Name
William Manetta
Agency Name
Castaic Lake Water Agency
Contact Types
Lead/Public Agency

Location

Cities
Santa Clarita
Counties
Los Angeles
Cross Streets
Canyon Road
Parcel #
2812-009-902
Waterways
Santa Clara River

Notice of Determination

Approving Agency
Castaic Lake Water Agency
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes