Venice Pumping Plant Dual Force Main

4 Documents in Project

Summary

SCH Number
2003031001
Lead Agency
Los Angeles, City of (City of Los Angeles)
Document Title
Venice Pumping Plant Dual Force Main
Document Type
NOD - Notice of Determination
Received

Document Description
Construct and operate a 54-inch diameter force main sewer extending about two miles from the existing Venice Pumping Plant at 140 Hurricane Street, eastward under the Grand Canal and along Marquesas Way, then southeasterly on Via Marina and portions of Marina Del Rey Public Parking Lot 13, then under the Marina Del Rey entrance and Ballona Creek channels to a point on the south side of Ballona Creek at Pacific Avenue. From there, the alignment continues south along Pacific Avenue and Vista Del Mar to the connection in Vista Del Mar near Waterview Street.

Contact Information
James E. Doty
Los Angeles Bureau of Engineering
650 S. Spring Street, Room 574
Los Angeles, CA 90014

(213) 847-8694

Location

Cities
Los Angeles
Counties
Los Angeles
Cross Streets
Hurricane Avenue / Grand Canal Esplanade to LAX
Zip
90292
Total Acres
Varies: subterra
State Highways
91 Freeway
Airports
LAX
Schools
Various; depending upon alignment
Waterways
Venice Canals, Ballona Lagoon, Pacific Ocean within Dual Coastal Zone
Township
2S
Range
15W
Section
Unsect
Base
SB
Other Location Info
Communities: Venice, Playa del Rey

Notice of Determination

Approving Agency
City of Los Angeles City Council
Approving Agency Role
Lead Agency
Approved On
Final EIR Available Location
Office of the City Clerk Room 395 of City Hall or Bureau of Engineering files at: 1149 South Broadway, Suite 600 Los Angeles, CA 90015-2213

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A Statement of Overriding Considerations was adopted for this project
Yes
(5) Findings were made pursuant to the provisions of CEQA
N/A