Temporary Water Right Permit for Santa Margarita Water District Multipurpose Basin Project
39 Documents in Project
Download CSV
New Search
Print
Summary
- SCH Number
- 2003021141
- Lead Agency
- Orange County
- Document Title
- Temporary Water Right Permit for Santa Margarita Water District Multipurpose Basin Project
- Document Type
- NOD - Notice of Determination
- Received
- Posted
- 11/25/2013
- Present Land Use
- A-1 General Agricultural and SG-Sand and Gravel Extraction.
- Document Description
- Santa Margarita Water District filed an application for a temporary permit to appropriate water on September 16, 2013 pursuant to Water Code section 1425. The district proposes to divert return flows from purchased water flowing Gobernadora Creek. An upper basin will use a wetland process to treat non-storm flows for irrigation use within the Coto de Caza community. A lower basin will be used to attenuate storm flows. A portion of the water diverted will be stored in the District Portola reservoir. The temporary permit is necessary to reduce the District's reliance on imported water and prevent the imminent loss of grant defunding for the project.
- Contact Information
-
Mitchell Moody
State Water Resources Control Board
Lead/Public Agency
Division of Water Rights 1001 I St.
Sacramento, CA 95812
Phone : (916) 341-5383
Location
- Cities
- San Juan Capistrano
- Counties
- Orange
- Regions
- Unincorporated
- Total Acres
- ~ 22,815
- State Highways
- 74
Notice of Determination
- Approving Agency
- State Water Resources Control Board
- Approving Agency Role
- Responsible Agency
- Approved On
- Final Environmental Document Available at
- Orange County 300 N Flower St., Santa Ana, CA 92703
Determinations
- (1) The project will have a significant impact on the environment
- Yes
- (2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
- Yes
- (2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
- No
- (2c) An other document type was prepared for this project pursuant to the provisions of CEQA
- No
- (3) Mitigated measures were made a condition of the approval of the project
- Yes
- (4) A mitigation reporting or monitoring plan was adopted for this project
- N/A
- (5) A Statement of Overriding Considerations was adopted for this project
- No
- (6) Findings were made pursuant to the provisions of CEQA
- Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.