Supplemental Program Environmental Impact Report for the 2013 Regional Water Facilities Optimization and Master Plan Update and Climate Action Plan

6 Documents in Project

Summary

SCH Number
2003021052
Lead Agency
San Diego County Water Authority
Document Title
Supplemental Program Environmental Impact Report for the 2013 Regional Water Facilities Optimization and Master Plan Update and Climate Action Plan
Document Type
NOD - Notice of Determination
Received
Posted
4/16/2014
Present Land Use
Various
Document Description
The 2013 Regional Water Facilities Optimization and Master Plan Update functions as a roadmap for implementing capital improvement projects needed to assure delivery system reliability and serve projected water demands in the San Diego region. This document updates 2003 Master Plan, focusing on the project modifications needed before 2035. These proposed project modifications include the P3/P4 Conversion Project, System Isolation Valves, System Regulatory Storage, the San Vicente 3rd Pump Drive and Power Supply and Asset Management Program. The Climate Action Plan identifies the Water Authority's current emissions, projected future emissions, emission reduction goals, and Energy Conservation Opportunities, and was prepared to serve as a qualified greenhouse gas reduction plan under CEQA Guidelines Section 15183.5.

Contact Information

Name
Ms. Kelley Gage
Agency Name
San Diego County Water Authority
Contact Types
Lead/Public Agency

Location

Counties
San Diego
Regions
Countywide
Cross Streets
County wide
Zip
multiple
Total Acres
657
Parcel #
County wide
State Highways
I-15; SR-79, 76, 78, 67
Schools
multiple

Notice of Determination

Approving Agency
San Diego County Water Authority
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
N/A

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print