Fallon Road Bridge Replacement Over Santa Ana Creek

4 Documents in Project

Summary

SCH Number
2003011150
Lead Agency
San Benito County
Document Title
Fallon Road Bridge Replacement Over Santa Ana Creek
Document Type
NOD - Notice of Determination
Received
Posted
6/10/2003
Present Land Use
County of San Benito General Plan Designation (Revised 1998): M, Industrial. County of San Benito Zoning Designation: the west side of the bridge is designated R1, Residential District and the east side of the bridge is designated FP, Flood Plain.
Document Description
The proposed project consists of the replacement of the Fallon Road Bridge (Bridge Number 43C-0032) over the Santa Ana Creek, in order to restore vehicular access across the Santa Ana Creek and to increase the level of earthquake safety for traffic on Fallon Road. The new bridge will essentially be constructed along the original alignment, within the existing right-of-way. The proposed bridge will be approximately 40'-8" wide, 60' long and will have two 12' lanes and 8' shoulders. The replacement bridge will be approximately six feet wider on each side than the existing bridge. The two-span bridge will be built on the same alignment as the existing bridge and will require the contractor to install six piles across the creek channel and associated wetlands, which is a reduction in the number of piles from the existing bridge.

Contact Information

Name
Dale Rosskamp
Agency Name
San Benito County Public Works Department
Contact Types
Lead/Public Agency

Location

Cities
Hollister
Counties
San Benito
Cross Streets
Fallon Road and Santa Ana Creek
State Highways
156
Airports
Municipal Airport

Notice of Determination

Approving Agency
San Benito County
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print