Reconstruction of Berth 22 Wharf and Reconfiguration of Adjacent Yards
3 Documents in Project
Summary
SCH Number
2002122016
Lead Agency
Port of Oakland
Document Title
Reconstruction of Berth 22 Wharf and Reconfiguration of Adjacent Yards
Document Type
NOD - Notice of Determination
Received
Posted
1/31/2003
Present Land Use
General Industrial/Transportation
Document Description
The main objectives of the project are to reconstruct the Berth 22 wharf to bring it to modern standards and to consolidate the yards of Berths 20 through 24. The project would include excavation and reconstruction of the Berth 22 embankment and dike to increase their seismic stability, reconstruction of the wharf, replacing the 2 existing cranes with 2 Post-Panamax cranes, and reconstructing the Berth 22 water and power supply as needed to serve the new facilities. The project would also include minor improvements to the Berths 21 through 24 yards such as removing fences and adjusting the pavement, demolishing buildings, relocating scales from Berth 24 gate to the Berth 21 gate (which will become the inbound gate for the Maersk-SeaLand terminal); closing the gate at Berth 23; and transforming the Berth 24 gate into the main outbound gate for the terminal. A portion of the Berth 24 project site is designated as a site in the list of hazardous materials sites compiled pursuant to Government Code 65962.5 ("Cortese List"). With implementation of mitigation measures identified in the Initial Study, potential significant impacts would be avoided, minimized, or reduced to a less than significant level.
Contact Information
Name
Marucia Britto
Agency Name
Oakland, Port of
Contact Types
Lead/Public Agency
Phone
Location
Cities
Oakland
Counties
Alameda
Cross Streets
Maritime and Chungking Street
Zip
94607
Total Acres
10
Parcel #
0-320-1, 0-350-1
State Highways
I-880, 580
Railways
Union Pacific, BNSF
Waterways
Outer Harbor, San Francisco Bay
Notice of Determination
Approving Agency
Port of Oakland
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
N/A