Felicita Avenue/Juniper Street CIP Street Widening Project

Summary

SCH Number
2002121094
Lead Agency
City of Escondido
Document Title
Felicita Avenue/Juniper Street CIP Street Widening Project
Document Type
NEG - Negative Declaration
Received
Present Land Use
Surrounding properties along the project area roadway segment are zoned for both single and multi-family residential uses. Current uses along the project area include single and multi-family residences and churches.
Document Description
The proposed project is a City of Escondido Capital Improvement Project to widen Felicita Avenue and Juniper Street in conformance with the City's General Plan (a total distance of approximately 1 mile). The project will be constructed in two phases. Phase 1 includes the widening of Juniper Street between 14th and 15th Avenues. The roadway width will be 64 feet from curb to curb, with 2 lanes in each direction and a left-turn lane. A portion of this widening (west side of Juniper Street, from Fifteenth Avenue to the Felicita Village condominium project entry drive) will be improved by the developers of Escondido Tract 841 (not a part of this City project). Additional improvements along 15th from Juniper to Broadway will include curb, gutter sidewalks and streetlights. In addition, the intersection of 15th/Juniper/Idaho will be realigned, and a traffic signal will be installed at that location. Water line replacement and storm drain upgrades will also be constructed at Juniper Street and Idaho Street. Three partial acquisitions will be required with Phase 1. Phase 2 will include the widening of Felicita Avenue between Escondido Boulevard and Juniper Street. This will consist of widening the existing two-lanes to full major roadway width. The width will vary between seventy nine to eighty-two feet curb to curb with two travel lanes in each direction and a raised median with left turn pockets provided at selected intersections. The widening of Juniper Street between Felicita Avenue and Chestnut Street consists of widening the existing two-lanes to full collector street width. The roadway width will be sixty-four feet from curb to curb, with two lanes in each direction and a left turn lane. New traffic signals will be installed at the intersections of Chestnut/Juniper (which will be realigned to the north to form a T-intersection with Juniper) and 13th/Juniper. This project will require the full acquisition of four privately owned parcels and partial acquisition of eight properties along the project frontage. Bike lanes will be provided with the implementation of the project along Felicita and Juniper.

Contact Information

Name
Cheryl Kitzerow
Agency Name
City of Escondido
Contact Types
Lead/Public Agency

Location

Cities
Escondido
Counties
San Diego
Cross Streets
Felicita Avenue and Juniper Street
Zip
92025
State Highways
15
Schools
Juniper School
Waterways
Escondido Creek

Notice of Completion

State Review Period Start
State Review Period End
State Reviewing Agencies
California Department of Fish and Wildlife, South Coast Region 5 (CDFW), California Department of Parks and Recreation, California Department of Transportation, District 11 (DOT), California Native American Heritage Commission (NAHC), California Regional Water Quality Control Board, San Diego Region 9 (RWQCB), California State Lands Commission (SLC), Department of Water Resources, Office of Historic Preservation, Resources Agency
Development Types
Transportation:Other (Street Widening)
Local Actions
Street Widening
Project Issues
Cultural Resources, Land Use/Planning, Noise, Transportation

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.