New Colgate Powerhouse Tailwater Depression Project

2 Documents in Project

Summary

SCH Number
2002092087
Lead Agency
Yuba County Water Agency
Document Title
New Colgate Powerhouse Tailwater Depression Project
Document Type
NOD - Notice of Determination
Received
Posted
11/18/2002
Document Description
The Yuba County Water Agency will install a tailwater depression system at New Colgate Powerhouse. The project involves the installation within the existing powerhouse facility of fabricated equipment that will provide for tailwater depression during higher flows, and operation of the new equipment to maintain powerhouse operations under high-flows conditions that historically required to shutdown of the powerhouse. The objective of these improvements is to enhance the Agency's ability to regulate flood inflow to New bullards Bar Reservoir by providing for additional reservoir release capacity through the powerhouse facilities in advance of and during flood flows. To power the new equipment, an electrical line will be extended from an existing transmission line on the slope north of the powerhouse to three new blowers, and associated electrical equipment will be installed near the powerhouse at the base of the slope and within the powerhouse yard. The project is expected to increase power generation by approximately 328,000 megawatt hours over a 50-year period.

Contact Information

Name
Curt Aikens
Agency Name
Yuba County Water Agency
Contact Types
Lead/Public Agency

Location

Counties
Yuba
Cross Streets
Lake Francis Road
Zip
95935
Total Acres
1 or less
Parcel #
43381-1
Waterways
Yuba River
Township
18N
Range
6E
Section
16
Base
MDBVM
Other Location Info
City: Dobbins

Notice of Determination

Approving Agency
Yuba County Water Agency
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
N/A

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print