Fiddyment Ranch F-44B Sewer and F-8B Swale Project (Streambed Alteration Agreement No .1600-2017-0041-R2)

33 Documents in Project

Summary

SCH Number
2002082057
Lead Agency
City of Roseville
Document Title
Fiddyment Ranch F-44B Sewer and F-8B Swale Project (Streambed Alteration Agreement No .1600-2017-0041-R2)
Document Type
NOD - Notice of Determination
Received
Posted
9/14/2017
Present Land Use
low density residential, public (schools), open space, parks
Document Description
CDFW has executed Lake and Streambed alteration Agreement no. 1600-2017-0041-R2, pursuant to section 1602o of the Fish and Game Code to the project Applicant, Signature Homes. Project is limited to two sub-projects associated with the construction of the Fiddyment Ranch portion of the West Roseville Specific Plan Open Space Preserve. Project consists of the following sub-projects: 1) Installation of a sewer pipeline under Pleasant Grove Creek. Construction of the F-44B Sewer will include excavating a trench through the creek to install two 6-inch one 12-inch sewer pipelines; installation of manholes at each end of the sewer pipes; and construction of paved roads and hammerhead turnarounds along the north and south sides of the creek to access each manhole. Following installation of the pipe, the creek's bed, banks, and channel will be returned to their original state and revegetated. A coffer dam will be installed upstream fo the work area to prevent flows from entering the work site, and the water will be pumped through a pipe around the work site and back into the creek downstream. Construction of a drainage swale to convey runoff into Pleasant Grove Creek. The F-8B outfall swale will be excavated between the creek and the future residential development. Riprap check dams will be instlaled in the created swale to reduce the flow velocity. Following construction, the swale will be stabilized using native seed mix and mulch.

Contact Information

Name
Gabriele Quillman
Agency Name
CDFW
Contact Types
Lead/Public Agency

Location

Cities
Roseville
Counties
Placer
Cross Streets
Fiddyment Road & Blue Oaks, Hayden Parkway
Zip
95747
Total Acres
805
Parcel #
several
Schools
Junction ES and West Roseville HS
Waterways
Pleasant Grove Creek

Notice of Determination

Approving Agency
CDFW
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.

Download CSV New Search Print