First Street Sewer
Document Type
NOD - Notice of Determination
Received
Posted
10/21/2002
Present Land Use
City of Temecula land use/Commercial and Residential Zoning/City of Temecula General Plan
Document Description
Eastern Municipal Water District proposes to abandon the existing First Street Sewer Lift Station and sewer force main and install a new sewer pipeline. The 30 year old First Street Sewer Lift Station, which conveys raw sewage to the Temecula Valley Regional Water Reclamation Facility for treatment, has exceeded its capacity and useful life. The District has determined that it will be more efficient and economical to install new 15-inch gravity sewer pipeline to convey sewage flows to the TVRWRF via the new Pujol Lift Station. The proposed project consists of installation of approximately 320 lineal feet of sewer pipeline across Murrieta Creek on the south side of First Street and approximately 200 lineal feet of sewer pipeline under First Street east of the bridge. Both the existing First Street Sewer Lift Station and sewer force main will be abandoned.

Contact Information

Name
Karen Hackett
Agency Name
Eastern Municipal Water District
Contact Types
Lead/Public Agency

Location

Cities
Temecula
Counties
Riverside
Cross Streets
First Street adjacent to the First Street Bridge
Zip
92592
Total Acres
1/2
Parcel #
Book 922, Page 10
State Highways
15/215
Waterways
Murieta C reek
Township
8S
Range
3W
Base
SBB&M

Notice of Determination

Approving Agency
Eastern Municipal Water District
Approving Agency Role
Lead Agency

Determinations

(1) The project will have a significant impact on the environment
N/A
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.