Los Esteros Critical Energy Facility
5 Documents in Project
Summary
SCH Number
2002079013
Lead Agency
California Energy Commission
Document Title
Los Esteros Critical Energy Facility
Document Type
NOD - Notice of Determination
Received
Posted
1/26/2004
Document Description
Acceptance of previously made modifications: substitute a shorter temporary transmission tap line in place of the underground connection to the PG&E Los Esteros Substation that was originally licensed.
Contact Information
Name
Lance Shaw
Agency Name
California Energy Commission
Contact Types
Lead/Public Agency
Phone
Location
Cities
San Jose
Counties
Santa Clara
Notice of Determination
Approving Agency
California Energy Commission
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
N/A
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.