Delta Pond Diffuser - Discharge Outfall Replacement
28 Documents in Project
Summary
SCH Number
2002072046
Lead Agency
City of Santa Rosa
Document Title
Delta Pond Diffuser - Discharge Outfall Replacement
Document Type
NOD - Notice of Determination
Received
Posted
10/29/2012
Document Description
The Project consists of the installation of recommended Management Practices (MP's) to repair stream crossings that are currently eroding or threatening to erode within the Pepperwood Preserve. Site specific erosion control treatments for eroding stream crossings would include installing critical dips to prevent stream diversions; cleaning, installing, and replacing culverts at stream crossings; decommission crossings, installing rock armor to prevent erosion; excavating soil at fills lopes and crossings; installing wet crossing with armor, and installing road drains, relief culverts, culvert downspouts, out slopes, and rolling dips.
Contact Information
Name
Charles Reed
Agency Name
Regional Water Quality Control Board
Contact Types
Lead/Public Agency
Phone
Location
Cities
Cotati, Healdsburg, Rohnert Park, Rohnert Park, Sebastopol, Windsor, Healdsburg, Cotati, ..., Santa Rosa, Sebastopol, Windsor
Counties
Lake, Sonoma
Cross Streets
Numerous
Total Acres
up to 35,000
Parcel #
Numerous
State Highways
101, 116, 12, 128, 175
Railways
Northwestern Pacific
Airports
Sonoma, Healdsburg, Cloverdale
Waterways
Russian River, Petaluma River, and several creeks
Base
MDB&M
Notice of Determination
Approving Agency
Regional Water Quality Control Board
Approving Agency Role
Responsible Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.