March Business Center

20 Documents in Project

Summary

SCH Number
2002071089
Lead Agency
March Joint Powers Authority
Document Title
March Business Center
Document Type
NOD - Notice of Determination
Received
Posted
3/28/2006
Present Land Use
The majority of land is currently undeveloped and unoccupied. General Plan land uses include Industrial, Business Park, Mixed Use, Commercial, Public Facility, Park/Recreation/Open Space and Destination Recreation.
Document Description
Design approval PP 05-05 for three buildings located on one 3.04-acre lot at 14625, 14635, and 14645 Meridian Parkway within the March Business Center (Meridian) development. The development consists of three tilt-up concrete buildings finished in earthtone colors consistent with the March Business Center Design Guidelines. The project is consistent with the Industrial land use designation identified in the March JPA General Plan, and the March Business Center Specific Plan. Approval of Industrial development on this site was fully analyzed in the Focused EIR for March Business Center. The approval incorporates all existing mitigation measures approved in the March Business Center Focused EIR.

Contact Information

Name
Dan Fairbanks
Agency Name
March Joint Powers Authority
Contact Types
Lead/Public Agency

Location

Cities
Moreno Valley, Riverside
Counties
Riverside
Cross Streets
SWC Alessandro Boulevard / I-215
Zip
92518
Total Acres
1,290
State Highways
SR 60, I-215
Railways
Burlington Northern Santa Fe
Airports
March Inland Port/ March ARB
Schools
Arnold Heights Elementary
Township
3S
Range
4W
Section
14,15,
Base
SanBerna
Other Information
Base: 22,23,28

Notice of Determination

Approving Agency
March Joint Powers Authority
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.

Download CSV New Search Print