March Business Center

20 Documents in Project

Summary

SCH Number
2002071089
Lead Agency
March Joint Powers Authority
Document Title
March Business Center
Document Type
NOD - Notice of Determination
Received
Posted
3/12/2003
Present Land Use
The majority of land is currently undeveloped and unoccupied. General Plan land uses include Industrial, Business Park, Mixed Use, Commercial, Public Facility, Park/Recreation/Open Space and Destination Recreation.
Document Description
CDFG is executing a Lake and Streambed Alteration Agreement (SAA #6-2002-291) pursuant to Section 1601 of the Fish and Game Code with the project applicant. The applicant (March Joint Powers Authority) proposes to develop the 1,290 acre-site with 44 acres of office use, 38 acres of commercial use, 125 acres of mixed use, 539 acres of business park, 370 acres of industrial use and 174 acres of park/recreation/open space use. The applicant is proposing to impact 0.40 acre of ephemeral/intermittent channels, 0.64 acre of concrete-lined channels, 0.12 acre of perennial channels and a 1.52 acre riparian area. As mitigation, the applicant proposes a vegetated 2.9 acre detention basin and 0.4 acre of created riparian channel.

Contact Information

Name
Dan Fairbanks
Agency Name
March Joint Powers Authority
Contact Types
Lead/Public Agency

Location

Cities
Moreno Valley, Riverside
Counties
Riverside
Cross Streets
SWC Alessandro Boulevard / I-215
Zip
92518
Total Acres
1,290
State Highways
SR 60, I-215
Railways
Burlington Northern Santa Fe
Airports
March Inland Port/ March ARB
Schools
Arnold Heights Elementary
Township
3S
Range
4W
Section
14,15,
Base
SanBerna
Other Information
Base: 22,23,28

Notice of Determination

Approving Agency
CDFG
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
N/A
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes