Unit G-1 Pipeline and Denk Reservoir Inflow/Outflow

4 Documents in Project

Summary

SCH Number
2002061045
Lead Agency
Olivenhain Municipal Water District
Document Title
Unit G-1 Pipeline and Denk Reservoir Inflow/Outflow
Document Type
NOD - Notice of Determination
Received
Posted
5/18/2004
Present Land Use
Existing land use: utility easements and vacant. Zoning: not applicable to pipeline. General Plan Designations: residential, open space, ecological resource/open space/park, prime arterial and secondary arterial.
Document Description
CDFG is executing a Lake and Streambed Alteration Agreement pursuant to Section 1601 (SAA #R5-2003-0147) of the Fish and Game Code to the project applicant, Mr. David C. McCollum, representing the Olivenhain Municipal Water District. The applicant proposes to alter the streambed of Copper Creek and two unnamed drainages, tributaries to Escondido Creek, tributary to San Elijo Lagoon and two unnamed drainages, tributaries to Encinitas Creek, tributary to Batiquitos Lagoon, to accommodate the construction of the Unit G-1 Pipeline and Denk Reservoir Inflow/Outflow Project. The project is comprised of constructing a potable water pipeline to connect to a recently completed water treatment plant.

Contact Information

Name
George Biest
Agency Name
Olivenhain Municipal Water District
Contact Types
Lead/Public Agency

Location

Cities
Carlsbad, Encinitas
Counties
San Diego
Zip
92024
Schools
La Costa Canyon High School
Waterways
Escondido Cr., San Marcos Cr., and tributaries
Township
12&13S
Range
3W
Section
4,5,32
Base
SanBerna

Notice of Determination

Approving Agency
CDFG
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print