Red Bluff Diversion Dam Fish Passage Improvement Project
6 Documents in Project
Summary
SCH Number
2002042075
Lead Agency
Tehama Colusa Canal Authority
Document Title
Red Bluff Diversion Dam Fish Passage Improvement Project
Document Type
NOD - Notice of Determination
Received
Posted
6/5/2008
Present Land Use
Government and General Industrial (Tehama County)
Document Description
Project facilities will include construction of a pumping plant at the Mill Site with an initial installed capacity of 2,180 cubic feet per second (cfs) and a footprint that will allow expansion to 2,500 cfs, if necessary. Prior to completing construction of the new pumping plant, the current 4-month gates-in operation (May 15 through September 15) will continue.
Contact Information
Name
Jeff Sutton
Agency Name
Tehama-Colusa Canal Authority
Contact Types
Lead/Public Agency
Phone
Location
Cities
Red Bluff, Tehama
Counties
Tehama
Cross Streets
Road 99W/Altube Avenue
Zip
96080
Total Acres
30
Parcel #
035-047-006/007/009/016
State Highways
99 & 36
Railways
Union Pacific
Airports
Red Bluff Municipal
Schools
Visa/Sac. River Discover Center
Waterways
Sacramento River, Red Bank Creek
Township
27N
Range
3W
Section
33
Notice of Determination
Approving Agency
Tehama-Colusa Canal Authority
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.