Mt. San Antonio College 2012 Facility Master Plan (Lake or Streambed Alteration Agreement No. 1600-2015-0022-R5)

21 Documents in Project

Summary

SCH Number
2002041161
Lead Agency
Mt. San Antonio Community College
Document Title
Mt. San Antonio College 2012 Facility Master Plan (Lake or Streambed Alteration Agreement No. 1600-2015-0022-R5)
Document Type
NOD - Notice of Determination
Received

Document Description
CDFW has executed Lake and Streambed Alteration Agreement No. 1600-2015-0022-R5, pursuant to section 1602 of the Fish and Game Code to the project Applicant, Mount San Antonio Community college District, as represented by Mr. Michael Gregoryk. The project is limited to the grading of two, unimproved and unnamed ephemeral streambeds (tributaries to Snow Creek) to accommodate future access and to accommodate a building pad for the approx. 2 megawatt photovoltaic solar project on approx. 17.22 acres. The project would impact 0.06 acres of mule fat scrub and 0.14 acres of sparsely vegetated ephemeral streambed, which will be mitigated through the creation of 0.20 acre, and restoration and preservation of no less than 0.12 acre of mule fat scrub.

Contact Information
Victoria Chau
CDFW
3883 Ruffin Road
San Diego, CA 92123

562-430-5082

Location

Coordinates
34°44'30"N 117°50'45"W
Cities
Walnut
Counties
Los Angeles
Cross Streets
N. Grande Avenue and Temple Avenue
Zip
91789
Total Acres
150
State Highways
Hwy 57, 60
Schools
Westhoff, Collegewood

Notice of Determination

Approving Agency
CDFW
Approving Agency Role
Responsible Agency
Approved On
Final EIR Available Location
3883 Ruffin Road, San Diego, CA 92123

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A Statement of Overriding Considerations was adopted for this project
No
(5) Findings were made pursuant to the provisions of CEQA
Yes