2002 and 2005 Rate of Progress Plan

2 Documents in Project

Summary

SCH Number
2002041088
Lead Agency
San Joaquin Valley Air Pollution Control District
Document Title
2002 and 2005 Rate of Progress Plan
Document Type
NOD - Notice of Determination
Received
Posted
6/10/2002
Present Land Use
n/a
Document Description
In December 2001, the reclassification of the San Joaquin Valley Air Basin (SJVAB) to severe nonattainment for the One-Hour Ozone National Ambient Air Quality Standard became final. The reclassification resulted from the failure of the SJVAB to attain the Standard by November 15, 1999 as required for serious nonattainment areas. Under the severe classification, the District is required to prepare plans which demonstrate attainment of the standard by November 15, 2005 and rate of progress plans (ROP)s that demonstrate that ozone precursors are reduced at a rate of three percent per year, averaged over three year periods. This plan fulfills the ROP requirements for 2002 and 2005. This plan does not address the requirement that the District demonstrate attainment of the standard.

Contact Information

Name
Tom Jordan
Agency Name
San Joaquin Valley Air Pollution Control District
Contact Types
Lead/Public Agency

Location

Counties
San Joaquin
Cross Streets
n/a
Zip
n/a
Total Acres
n/a
Parcel #
n/a
State Highways
n/a
Railways
n/a
Airports
n/a
Schools
n/a
Waterways
n/a
Other Location Info
8 counties in the San Joaquin Valley

Notice of Determination

Approving Agency
San Joaquin Valley Unified Air Pollution Control District
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print