Greenfield Drive Project
2 Documents in Project
Summary
SCH Number
2002041060
Lead Agency
San Diego County
Document Title
Greenfield Drive Project
Document Type
NOD - Notice of Determination
Received
Posted
6/14/2002
Present Land Use
Urban Residential and General Commercial
Document Description
This project is the improvement of the intersection of Greenfield Drive and 1st Street in the unincorporated community of Bostonia. A traffic signal will be installed and Greenfield Drive will be widened approximately 12 feet to accommodate a new right turn lane for eastbound Greenfield Drive turning onto southbound 1st Street. In addition, a new underground storm drain system will be constructed to convey runoff from the intersection to the existing storm drain system approximately 800 feet west of the intersection. All of the improvements will occur within the right-of-way. An approximately 12-foot by 40-foot section of right-of-way will be acquired from the property owner on the corner adjacent to the new turn lane.
Contact Information
Name
Steve Ron
Agency Name
San Diego County, Department of Public Works
Contact Types
Lead/Public Agency
Phone
Location
Counties
San Diego
Cross Streets
Greenfield Drive and 1st Street
State Highways
8,67
Railways
San Diego Trolley
Airports
Gillespie Field
Waterways
Forrester Creek and Washington Channel
Township
16S
Range
1W
Section
ElCajo
Notice of Determination
Approving Agency
County of San Diego Board of Supervisors
Approving Agency Role
Responsible Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
N/A
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.