CA Endangered Species Act Incidental Take Permit (ITP) No. 2081-2010-031-03
32 Documents in Project
Summary
SCH Number
2002032132
Lead Agency
Freeport Regional Water Authority
Document Title
CA Endangered Species Act Incidental Take Permit (ITP) No. 2081-2010-031-03
Document Type
NOD - Notice of Determination
Received
Posted
4/21/2011
Present Land Use
Linear project crossing numerous parcels with various land uses, zoning designations, and general plan land use designations.
Document Description
The project involves the construction and operation of a new water intake facility on the Sacramento River in conjunction with a new water pipeline from the intake facility to the Folsom South Canal in eastern Sacramento County, a new water treatment plant in central Sacramento County, a new water pipeline from the southern terminus of the Folsom South Canal to the East Bay Municipal Utility District's Mokelumne Aqueduct in San Joaquin County, and two water pumping stations between the Folsom South Canal and Mokelumne Aqueduct.
Contact Information
Name
Carl Wilcox
Agency Name
Dept. of Fish and Game
Contact Types
Lead/Public Agency
Phone
Location
Cities
Sacramento
Counties
Sacramento, San Joaquin
Cross Streets
Multiple
Zip
Multiple
Parcel #
Multiple
State Highways
160, 5, 99, 12, 88, 49
Railways
Union Pacific,Southern Pacific
Airports
Sac.International, Sac.Executive
Schools
Multiple
Waterways
Sacramento River, Mokelumne River
Township
7N/5N
Range
4E/10E
Section
11/28
Base
Clarksbu
Notice of Determination
Approving Agency
Dept. of Fish and Game
Approving Agency Role
Responsible Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.