Motoike Dam Project

2 Documents in Project

Summary

SCH Number
2002022104
Lead Agency
Stockton East Water District
Document Title
Motoike Dam Project
Document Type
NOD - Notice of Determination
Received
Posted
4/8/2002
Present Land Use
0450 Ind, Field Crop only, Irrigated 0411 Ind, Nut Orchard, Irrigated, Res
Document Description
The project will involve the construction of a 5 foot high by 50 foot wide flashboard dam within the normally dry north fork of Potter Creek, to be installed annually for irrigation purposes during April 1 - October 15. The completion date is anticipated to be 9/30/2002.

Contact Information

Name
Kevin Kauffman
Agency Name
Stockton East Water District
Contact Types
Lead/Public Agency

Location

Counties
San Joaquin
Parcel #
105-200-09&-10
Waterways
Mormon Slough, Potter Creek
Township
2
Range
8E
Section
27
Base
MD

Notice of Determination

Approving Agency
Stockton East Water District
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
N/A
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
N/A