Crystal Springs/El Centro Phase II Trunk Sewer Improvements Project (Project); Clean Water State Revolving Fund (CWSRF) No. C-0652402-110

8 Documents in Project

Summary

SCH Number
2002022058
Lead Agency
City of Hillsborough
Document Title
Crystal Springs/El Centro Phase II Trunk Sewer Improvements Project (Project); Clean Water State Revolving Fund (CWSRF) No. C-0652402-110
Document Type
NOD - Notice of Determination
Received
Posted
4/3/2015
Present Land Use
Residential
Document Description
The purpose of the Project is to enlarge the remaining undersized segments of the Town's Crystal Springs/El Cerrito Sewer Trunk. The Project will expand flow capacity of the sewer trunk by removing and replacing 12,530 linear feet of pipeline, reconnect laterals, connect other existing mains to the new pipeline, and abandon some older lines in place. Construction will be done by open trenching, with trench widths ranging from 18 to 40 inches. Some portions of the collection system, upper and lower laterals, are in poor condition and allow a substantial amount of inflow and infiltration during storm events, overloading the system's hydraulic capacity. The Project will also entail trench stabilization at four locations along the east side of El Cerrito Avenue, to increase the structural stability of the road shoulder, prevent the loss of stream bank vegetation, and reduce sediment loads to the San Mateo Creek.

Contact Information

Name
Ahmad Kashkoli
Agency Name
State Water Resources Control Board
Contact Types
Lead/Public Agency

Location

Cities
Hillsborough
Counties
San Mateo
Cross Streets
El Cerrito Avenue and Crystal Springs Road
Zip
94010
Parcel #
Various
State Highways
I-280, I-92
Schools
South School,Crystal Springs Upland, Park ES, Saint Bartholomew
Waterways
San Mateo Creek
Other Information
Schools: (Cont.): San Mateo Park Math and Science School, Aragon HS, College of San Mateo

Notice of Determination

Approving Agency
State Water Board
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes