Concurrence in the Issuance of a Revised Solid Waste Facilities Permit for South Valley Organics Composting Facility in Santa Clara County, SWIS No. 43-AA-0017

6 Documents in Project

Summary

SCH Number
2002022005
Lead Agency
Santa Clara County
Document Title
Concurrence in the Issuance of a Revised Solid Waste Facilities Permit for South Valley Organics Composting Facility in Santa Clara County, SWIS No. 43-AA-0017
Document Type
NOD - Notice of Determination
Received
Posted
7/30/2015
Document Description
Proposed changes include: An increase in the total permitted area from 18.3 acres to 46 acres. The permitted boundary will be expanded to include existing ancillary facilities such as the scale house, retention ponds, and pipelines which serve South Valley Organics compost operations; An increase in the permitted traffic volume from 260 vehicles per day to 341 vehicles per day. The total of 341 vehicles per day includes the composting facility, the transfer station, and the wood processing facility (all three facilities have separate Solid Waste Facility Permits); Removal of permit conditions that are obsolete or duplicative of existing regulations and/or the monitoring program; Updates to the Report of Composting Site Information (RCSI); Updates to the documents that describe and/or restrict the operation of the composting facility.

Contact Information

Name
Erik Kiruja
Agency Name
CalRecycle
Contact Types
Lead/Public Agency

Location

Cities
Gilroy
Counties
Santa Clara
Cross Streets
Highway 152/Bloomfield Avenue
Total Acres
18.3
Parcel #
841-41-010,841-41-012,841-41-016
State Highways
152

Notice of Determination

Approving Agency
CalRecycle
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
N/A

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.

Download CSV New Search Print