Santa Clara Valley Transportation Authority (SCVTA) Silicon Valley Berryessa Extension (SVBX) (former Silicon Valley Rapid Transit Corridor) - Advanced Utility

39 Documents in Project

Summary

SCH Number
2002022004
Lead Agency
Santa Clara Valley Transportation Authority
Document Title
Santa Clara Valley Transportation Authority (SCVTA) Silicon Valley Berryessa Extension (SVBX) (former Silicon Valley Rapid Transit Corridor) - Advanced Utility
Document Type
NOD - Notice of Determination
Received
Posted
11/14/2011
Present Land Use
Multiple
Document Description
The Operator proposes the following: 1) impact five drainages along the Silicon Valley Berryessa Extension (SVBX) Project alignment, 2) replacement of an existing Union Pacific Railroad bridge with a Bay Area Rapid Transit (BART) aerial guideway, 3) a double box culvert with new roadway bridge to Berryessa Station Way, and 4) installation of a drainage outfall to Coyote Creek. The SVBX Project consists of the first 9.9 miles of the larger 16.1-mile BART Silicon Valley Project. The SVBX Project begins from the BART Warm Springs Station in Fremont and terminated near Las Plumas Avenue in San Jose. The SVBX Project includes two stations: Milpitas Station in Milpitas and Berryessa Station in San Jose. The California Department of Fish and Game (DFG) is executing a Lake or Streambed Alteration Agreement Number 1600-2011-0303-3 pursuant to Section 1602 of the Fish and Game Code to the project Applicant, Ann Calnan, Senior Environmental Planner/ Santa Clara VTA.

Contact Information

Name
Dave Johnston
Agency Name
DFG, Bay Delta Region
Contact Types
Lead/Public Agency

Location

Cities
Fremont, Milpitas, San Jose, Santa Clara
Counties
Alameda, Santa Clara
Cross Streets
Multiple
Zip
multiple
Total Acres
~150
Parcel #
multiple
State Highways
Hwy 237,87,880, 689, 91
Railways
UPRR
Airports
no
Schools
multiple
Waterways
multiple
Township
5,6S
Range
1W
Section
10-38
Base
MDM&M

Notice of Determination

Approving Agency
California Transportation Commission
Approving Agency Role
Responsible Agency

Determinations

(1) The project will have a significant impact on the environment
N/A
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
N/A
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
N/A

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print