BART Silicon Valley Project, Phase I - Berryessa Extension

37 Documents in Project

Summary

SCH Number
2002022004
Lead Agency
Santa Clara Valley Transportation Authority
Document Title
BART Silicon Valley Project, Phase I - Berryessa Extension
Document Type
NOD - Notice of Determination
Received

Document Description
The BART Silicon Valley Project (formerly referred to as the Silicon Valley Rapid Transit Corridor or SVRTC Project) consists of a 16.1-mile extension of the Bay Area Rapid Transit (BART) system from the planned Warm Springs Station in Fremont through Milpitas and San Jose to Santa Clara. See Exhibit 1. Several design changes have occurred since the project was approved in 2007. The most substantial change is that the project would be constructed in phases, Although VTA is committed to building the full 16.1 mile extension, the current state of the economy requires that the project be built with a phased-construction approach.

Contact Information
Tom Fitzwater
Santa Clara Valley Transportation Authority
3331 N 1st Street
San Jose, CA 95134-1927

408-321-5705
408-321-5787

Location

Coordinates
37°20'15"N 121°53'15"W
Cities
Santa Clara San Jose Milpitas Fremont
Counties
Santa Clara Alameda
Cross Streets
Multiple
Zip
multiple
Total Acres
~150
Parcel #
multiple
State Highways
Hwy 237,87,880, 689, 91
Railways
UPRR
Airports
no
Schools
multiple
Waterways
multiple
Township
5,6S
Range
1W
Section
10-38
Base
MDM&M

Notice of Determination

Approving Agency
Santa Clara Valley Transportation Authority
Approving Agency Role
Lead Agency
Approved On
Final EIR Available Location
Santa Clara Valley Transportation Authority 3331 North 1st Street, San Jose, Ca 95134

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A Statement of Overriding Considerations was adopted for this project
Yes
(5) Findings were made pursuant to the provisions of CEQA
Yes