Avenue G Widening

4 Documents in Project

Summary

SCH Number
2002021066
Lead Agency
City of Lancaster
Document Title
Avenue G Widening
Document Type
NOD - Notice of Determination
Received
Posted
5/9/2003
Present Land Use
Regional Arterial, Light Industry Specific Plan (LISP)
Document Description
The proposed Avenue G improvement project is a two-part project: a) the widening of the existing Avenue G and b) the placement of a storm drain and water main. The project consists of a widening of Avenue G from an existing 2-lane (24-feet wide) road to a 6-lane (104-feet wide) road with a 14-foot wide raised median, curbs, and gutter. The final total new right-of-way will be 120 feet, which will include the widened roadbed and width reserved for future sidewalks, parkway, and driveway improvements. In addition, the project will include a new storm drain system and catch basins that will be installed as necessary to be consistent with teh City's Master Plan of Drainage. The proposed drainage project consists of constructing a combination of storm drain and water main improvements along Avenue G from 25th Street West to 50th Street West and south on 30th Street West and 50th Street West to Avenue H. Most of the drainage system would be placed under the existing roadways.

Contact Information

Name
Betty Courtney
Agency Name
Fish and Game
Contact Types
Lead/Public Agency

Location

Cities
Lancaster
Counties
Los Angeles
Cross Streets
25th Street West and 50th Street West
Total Acres
26
State Highways
14
Airports
Fox Field Airport (private)
Township
7N;8N
Range
12&13W
Section
5& 61&
Other Information
Section: 2, 35 & 36

Notice of Determination

Approving Agency
Fish and Game
Approving Agency Role
Responsible Agency

Determinations

(1) The project will have a significant impact on the environment
N/A
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
N/A
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
N/A

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.